The report knowledge highlighted that the speed of development, which stood at 37 km per day in FY21, has now dropped to 27 km per day in FY26 (projected).
The report famous that the slowdown is because of decrease awarding of initiatives, execution challenges, and plenty of Hybrid Annuity Mannequin (HAM) initiatives awaiting appointed dates (AD).
It additionally shared that execution tempo is predicted to say no by 7-10 per cent throughout FY26. On the similar time, the sector is witnessing elevated aggressive depth for NH-HAM bids, additional including strain on builders.
The report confirmed that after a powerful efficiency in FY18, when 17,065 km of initiatives have been awarded and 9,829 km have been constructed, the sector entered a slower section.
In FY19, undertaking awards fell sharply to five,493 km whereas development stood at 10,885 km. The tempo remained sluggish in FY20 as nicely, with 8,912 km awarded and 10,237 km constructed.A restoration was seen in FY21, when 10,467 km have been awarded and development rose to 13,435 km, pushing the day by day tempo to 37 km.Nonetheless, this momentum was not sustained. In FY22, undertaking awards elevated to 12,731 km however development was barely decrease at 10,457 km, bringing the tempo all the way down to 29 km per day.
FY23 witnessed wholesome undertaking awards of 12,375 km and development of 10,331 km, with the tempo at 28 km per day.
The next yr, FY24, noticed awards slowing once more to eight,581 km, whereas development rose to 12,349 km, and the tempo averaged 34 km per day.
However in FY25, awards dropped sharply to 4,874 km and development fell to 10,660 km, reducing the day by day tempo to 29 km. For FY26, the projection exhibits development at 9,900 km, which interprets to simply 27 km per day.
The info signifies that whereas India has seen durations of robust development in freeway development, current years have introduced vital challenges, and the general momentum has slowed down.